STEP #1: Thoroughly clean surface area free from all
dust, dirt and other loose materials, using a wire brush if
necessary. Stone Mason All Purpose Concrete Cleaner is recommended
to remove oil and grease contamination.
STEP #2: If temperature is 80°F (27°C) or above,
dampen area with water mist before applying.
STEP #3: Apply directly from container using a flexible
putty knife, broad knife or trowel. Press firmly into patch
area, smooth and feather edge. DO NOT OVER TROWEL.
STEP #4: Maximum application thickness is 1/4"
(0.6cm). For repairs up to 1" (2.5 cm) deep apply in
1/4" (0.6cm) layers, allowing each layer to dry overnight.
Stone Mason Vinyl Cement Patch is recommended for patches
greater than 1" (2.5cm) deep or 3" (7.6cm) wide.
STEP #5: Drying time: Allow 2-3 days for light traffic.
Stone Mason Vinyl Cement Patch is recommended for use in heavier
vehicular traffic areas.
STEP #6: Do not apply if rain is expected within 24
hours or if temperature is expected to drop below 40°F
(5°C).
STEP #7: Stone Mason Concrete Crack Filler is recommended
to seal joints where joint movement is anticipated.
Clean